Happy Valley Access Elevator Project
Whakapapa Ski Field, Mt Ruapehu
Craig Davison
$1.2M
Project Manager:
Circa:
Construction of a twin-elevator access tower and bridge within a UNESCO World Heritage alpine environment, delivered in a live public setting with safety and public separation paramount.
Fast-tracked $1.2m delivery ahead of the 2017 ski season, shaped by weather and programme constraints.
Extensive prefabrication to accelerate delivery, including a 22-metre steel tower constructed horizontally, fully clad and glazed, then lifted into position by double crane lift.
Complex sequencing alongside multiple concurrent fast-track projects, including overnight removal of the existing chairlift drive station to maintain uninterrupted skier access.